Capping Beam Removal by Wire Saw, Western Sydney
Client: infrastructure contractor (confidential). Location: Western Sydney NSW. Scope: capping beam removal from a temporary shaft by diamond wire saw and wall saw. Status: in progress, November 2026. This page will be updated when the beam is out. Capping beam removal
Waterproofing Membrane Removal on a Hospital Plant Deck, Birtinya
The job Frank Cole Waterproofing was re-waterproofing a plant deck at a hospital in Birtinya on the Sunshine Coast. The deck carries condensers, fan units, pipework and steel plant frames, and the old coating had to come off back to clean
Commercial Strip Out in an Airport Terminal, Brisbane
The job Quadric is a Brisbane builder working on commercial interiors and base build refurbishments. For a refurbishment inside an operating airport terminal at Brisbane Airport, they needed a crew to strip out a row of self service bag drop units
Rock Face Cutting and Coring, Arthur Street, North Sydney
The job Shotcrete Australia has been the head contractor on a rock face stabilisation job along Arthur Street in North Sydney, cutting and coring pockets and niches into a natural sandstone retaining wall that runs beside a busy public road. Perfect Concrete
Concrete Coring, Cutting and Scanning, Campbelltown Hospital
The job Taylor Construction Group has been the head contractor on works at Campbelltown Hospital, on Therry Road in Campbelltown. The job has covered plant and utility areas, services corridors and a valve station on the grounds, with new openings, cores
Concrete Coring and Cutting, Medlow Bath Station, Blue Mountains
The job Arenco was the builder on the upgrade of Medlow Bath Station in the Blue Mountains. The job took in new stairs, a footbridge connection, new drainage along the platform and new concrete work in the ground, and all of
Lift Shaft Concrete Repairs, Coring and Landing Door Openings, North Bondi NSW
The job Gartner Rose was carrying out lift shaft remediation in an existing building at an operating facility in North Bondi. Before the new landing door frames could go in, the concrete shaft needed work: the old fixings had to come
Platform Coping Reinforcement GPR Scanning, Sydenham to Bankstown Corridor
The job Perfect Concrete Care was engaged by the John Holland Laing O'Rourke Joint Venture (JHLOR JV) to locate and mark reinforcement in the platform coping along the Sydenham to Bankstown rail corridor. The JV needed to know exactly where the
Precision Cutting and Safe Removal of a Boundary Wall in Kirrawee
Perfect Concrete Care recently completed a specialised concrete cutting and removal project in Kirrawee, delivering a safe, fast and fully controlled solution for a client who required an obstructing boundary wall removed under extremely tight timeframes.Although the structure appeared simple
Wet Area Rectification & Surface Preparation, St Marys
Service: Pro Prep, Grinding, Surface Preparation & Patch Repairs Project Overview Perfect Concrete Care is delivering a targeted rectification program in wet areas alongside a full surface preparation package ahead of waterproofing. Our objective is to provide a clean, smooth and level substrate that enables