Homepage / Projects / Road Sawing – Wynyard Station – Sydney Trains

Road Sawing – Wynyard Station – Sydney Trains

Road Sawing - Wynyard Station - Sydney Trains

Perfect Concrete Care recently completed a project directly for Sydney Trains at Wynyard Station. The project’s main objective was to cut a channel along the platform edges which allowed a gap filler to be installed and close the gap from the trains to the platform.

Our team developed a methodology using our Husqvarna FS500 Road Saws to obtain precise cuts along the platform. Our road saw is capable of cutting depths of up to 680mm with millimetre precision.


The staff on-site from Perfect Concrete Care were very professional, competent, helpful and friendly to work with. They took initiative to complete the tasks allowed to them by our Sydney Trains Team. They came prepared with all the tools and equipment needed to get the job done.

Vinay Shankar
Project Engineer
Sydney Trains

One of the key challenges of the project was to control the concrete slurry that the road saws produce. Our client Sydney Trains must abide by strict EPA guidelines so there could be zero slurry allowed to fall off the platform and onto the tracks. Fortunately, we have a fleet of Tyrolit VCE 2000 slurry vacuums that make short work of any slurry produced.

Over the two weekend possessions, our concrete care operators managed to complete over 240 lineal meters of cutting on both platforms and completed our scope of work well within schedule.

  • Client
    Sydney Trains
  • Location
    Wynyard Station
  • Duration
    4 Nights

Commercial, Industrial & Infrastructure Projects

SEE MORE