Company

SYDNEY Head Office
4/8 Lilian Fowler Place
Marrickville NSW 2204
(02) 8015 6398

QUEENSLAND Office
23 Aranda Steet
Slacks Creek QLD 4127
(07) 2145 6581

Mon-Fri: 7am-5pm
Sat-Sun: Closed

info@perfectconcretecare.com.au

Rooftop Waterproof Membrane Removal and Grinding, Infinity Apartments, Hamilton QLD

Apartment rooftop slab ground back to bare concrete after waterproof membrane removal, Brisbane River and CBD behind, Hamilton Brisbane QLD

Project Details

Location

Infinity Apartments, Harbour Road, Hamilton QLD

Client

NCR National Construction and Remedial

Duration

July to August 2026

The job

Infinity Apartments is a residential building on Harbour Road at Hamilton in Brisbane, looking over the river towards the city. NCR, a remedial builder, was re-waterproofing the roof, and the old membrane had to come off first. The roof is a working plant deck, covered in air conditioning condensers, pipe runs, cable trays and hot water units, and all of it had to stay where it was.

NCR brought in Perfect Concrete Care to remove the membrane and prepare the slab. Our Queensland crew was on the roof from the start of July to early August 2026.

Rooftop plant deck of an apartment building covered in old black waterproof membrane, air conditioning units behind, Hamilton QLD
Before. The plant deck under the old black membrane, packed with condensers.
Old waterproof membrane on an apartment rooftop between rows of air conditioning condensers, Hamilton Brisbane
Membrane running under and between the plant, which stayed in place the whole job.
Walled rooftop plant area with old membrane partly lifted at the edges, apartment building in Hamilton QLD
An enclosed plant area before we started on it.

What the work involved

  • Breaking the old black waterproof membrane off the roof slab with electric breakers and lifting it in sheets
  • Bagging the removed membrane into bulk bags on the roof for removal
  • Hand grinding the adhesive left under the membrane back to bare concrete, with every grinder on a vacuum
  • Working under and around the condensers, pipe runs, supports, platforms and drains without moving or damaging any of them
  • Wall cutting with chasers in the last weeks of the job
  • Surface preparation across the whole roof so the waterproofer had a clean, sound slab to work on
Old membrane sheets lifted off a rooftop slab beside plant and pipework, Hamilton Brisbane
Membrane coming up in sheets once the breaker got under it.
Rooftop membrane removed from under pipe supports and a platform, breaker resting on the platform, Hamilton QLD, brand blurred
Working the membrane out from under pipe supports and platforms.
Rooftop slab with the membrane off and adhesive exposed, removed membrane in bulk bags behind, Hamilton Brisbane
Membrane off and bagged, the adhesive underneath next to be ground off.

What made it hard

Almost none of the roof was open slab. The membrane ran under rows of condensers, around pipe supports and beneath platforms and pipe racks. A floor grinder was no use in most of it, so nearly all the grinding was done by hand, in strips, around each piece of plant.

The plant stayed live the whole time. Pipework and cables had to be protected while breakers and grinders worked right next to them.

Everything came up to the roof and everything went back down. The membrane and grinding waste were bagged as the work went, and the deck was worked in sections so there was always somewhere clear to stand and stack bags.

Clean ground concrete meeting old black membrane under rooftop pipe runs on an apartment building in Hamilton QLD
Ground concrete on one side, old membrane on the other, under the pipe runs.
Rooftop area with membrane removed around large pipe runs and fittings, adhesive being ground off, Hamilton
Around the pipe runs, where everything was done by hand.
Rooftop deck edge with the membrane and adhesive being ground off beside a parapet, Hamilton Brisbane QLD
Grinding the adhesive off along the deck edge.

How it was done

Each section of roof was done in the same order. Breakers got under the membrane and lifted it off, the membrane went straight into bulk bags, then the crew hand ground the adhesive off with 130 and 150 mm grinders on shrouds and vacuums until only bare concrete was left.

Around the plant the crew worked in tight strips and by hand, under the pipe racks and along the base of each wall and platform. The roof was worked area by area, from the open sections through to the enclosed plant areas, until the whole deck was done.

Rooftop plant deck ground back to concrete under pipe runs and supports, city skyline behind, Hamilton QLD
Deck ground clean under the pipe runs, supports left where they were.
Walled rooftop plant area ground back to concrete after membrane removal, apartment building in Hamilton Brisbane
The same enclosed area, finished.
Rooftop slab ground clean around pipework and services against the wall, Hamilton QLD
Slab ground around the services along the wall.
Narrow rooftop strip between pipe racks ground back to bare concrete, Hamilton Brisbane
A narrow strip between pipe racks, ground clean.
Rooftop plant deck with membrane removed around pipe runs and condensers, Brisbane CBD behind, Hamilton QLD
Late in the job, most of the deck done around the plant.

Outcome

The whole rooftop was handed over as bare, clean concrete in early August 2026, with the condensers, pipe runs and hot water plant left where they were and working.

Open rooftop area finished to bare concrete after membrane removal, apartment buildings behind, Hamilton Brisbane QLD
Finished. Bare concrete, ready for the new membrane.

Lessons learned on this job

Every job teaches the crew something. These are the ones we took from Infinity Apartments.

What worked

  • Breaking the membrane off first and bagging it straight away, so the grinders were only ever working on adhesive and the deck stayed clear
  • Hand grinders on vacuums for almost everything, because the plant left no room for a floor machine
  • Working the roof section by section, so the waterproofer could see progress and the crew always had a clear area to work from

What was difficult

  • A roof packed with live plant, pipe runs and platforms, with the membrane running under all of it
  • Adhesive stuck hard to the slab under the membrane, which took far more grinding than the membrane itself
  • Getting every bag of waste off a rooftop plant deck

If you have something similar

Remedial builders, strata managers and waterproofers re-doing a roof with the plant still on it need the old membrane off without touching the services. Have a look at our coating and membrane removal, surface preparation and concrete grinding pages, see a similar rooftop job at Magnoli Apartments, Palm Beach, or get in touch and tell us what is on your roof.

Perfect Concrete Care, your trusted concrete solutions partner

Perfect Concrete Care cuts, cores, grinds and scans concrete on commercial and industrial sites. Our technicians run current plant, work to your programme and keep dust, water and noise under control so the rest of the site keeps moving.

We work for builders, civil contractors, facility managers and government across Sydney, Brisbane and South East Queensland. Most of our work is repeat work, which is the only reference that counts in this trade. Send us the drawings or call and we will price it properly.

Talk to a real personCall now

Aboriginal and Torres Strait Islander flagsPerfect Concrete Care acknowledges the Aboriginal and Torres Strait Islander people as Traditional Custodians of the country on which we live and work. We pay our respects to the Traditional Custodians and Elders past, present and future, and honour their connection to the land and ongoing contribution to society.