The job
Watertight Group brought Perfect Concrete Care in to scan and core drill sections of the Mechanical Engineering Building at the University of Sydney, Camperdown, ahead of waterproofing works to the rooftop and balcony areas.
The job ran from July 2025 to January 2026, on and off as waterproofing works progressed across different areas of the building, rather than one continuous run.


What we did
- Concrete scanning with ground penetrating radar to locate rebar and services before any drilling started
- Core drilling through rooftop slabs, balcony walls and roof membrane areas
- Marking out chalk scan grids on each section before coring
- Fitting pipe collars and seals to finished cores where required
- Working around an occupied academic building with staff and office space in use nearby


What made it hard
The building stayed in use throughout, with open plan office space right next to some of the work areas, so every scan and core had to be planned around people still working in the building.
Spreading the job out over several months rather than one continuous block meant resetting the work area each time, checking scans were still accurate, and coordinating around whatever waterproofing stage the building was up to.


How it was done
Each section started with a scan. The crew marked out a chalk grid and ran the ground penetrating radar over it to locate rebar and services before any drilling began, keeping every core clear of anything live in the slab.
Coring then went ahead through the marked sections, with finished cores fitted with pipe collars and seals where the waterproofing trade needed a clean penetration to work into.






Lessons learned on this job
Every job teaches the crew something. These are the ones we took from the University of Sydney job, and we use them on every scan and core job in an occupied building.
What worked
- Scan before every core, no exceptions. Ground penetrating radar over a marked chalk grid kept every drill clear of rebar and services
- Fitting collars and seals as soon as a core was finished, so each penetration was left ready for the waterproofing trade
- Resetting properly on each return visit, checking scans against the latest layout before picking tools back up
What was difficult
- An occupied academic building throughout, with office space right next to some work areas
- A job spread over several months rather than one continuous run, meaning the work area had to be reset each time
- Coordinating scanning and coring around whatever stage the waterproofing works were up to
If you have something similar
Waterproofing contractors and head contractors needing concrete scanning or core drilling in an occupied building should have a look at our concrete scanning Sydney and concrete core drilling Sydney pages, or get in touch.